Melvin and I continued with the high cladding at the west end of the house and made steady progress through the morning. I managed to fall about three feet from the scaffold and landed flat on my back. It winded me momentarily, and throughout the remainder of the day I became increasingly sore and immobile. Melvin was fitting the cladding while I operated the saw, and around lunchtime he finally topped out, fitting the last board from a step-ladder perched on the scaffold. It was actually one of the steadiest scaffold we've had - probably because we'd built it leaning in against the house wall.
Anna turned up, followed by Roger Lynn, the landscaper. They spent half-an-hour discussing his plan, and I asked Melvin to stick his oar in, as I've become a bit hacked off with Roger's lack of action, and would like Melvin to do the work. Anna managed a bit of painting before she nicked off on a schoool-run just before 3.
We lugged the saw down to the other end and carried on above the verandah, where I'd started over the weekend. A tricky and very slow section around windows, combined with my increasing stiffness and Melvin's sense of anti-climax at working from ground-level made it a slightly subdued afternoon, and we packed up just as light was fading around 4 p.m. I had quite a bit of dificulty getting from the roof onto the ladder, and even more getting out of the car when I got home. Think I might be a bit sluggish tomorrow...
271107 |
No comments:
Post a Comment